Scope of work (Low Current System)
Supply, install, configure, test, and commission all low-current and IT infrastructure systems for a three-floor office building with a total area of 2,800 m² and approximately 130 employees. The scope includes a fully equipped data center, structured cabling for data and IP telephony, a complete Cisco unified communication and wireless solution, physical access control for 34 doors, time attendance system, and a fully integrated conference room.
1. Server & Storage Hardware
Supply and install HP servers (model and quantity as per final specification) Windows Server Standard 2022 LTS, SQL Server (Standard or Enterprise edition as required), File Server & FTP server.
Synology storage system with usable capacity exceeding 120 TB (RAID protected). Configure with appropriate RAID level (RAID 6) and hot-spare drives.
2. Operating Systems & Applications
Install and license Microsoft Windows Server 2022 Standard LTS (number of licenses covering required physical or virtual cores).
Install and configure Microsoft SQL Server (licensing per core or server + 6 CAL).
Configure File Server with appropriate folder structures, NTFS permissions, and quota management.
Configure FTP Server (secure FTP over SSL/TLS) with user isolation and access logs.
3. Networking Hardware (Data Center Edge)
Supply and install routers (enterprise grade) for WAN connectivity and inter-VLAN routing.
Supply and install next-generation firewall with features: stateful inspection, IPS/IDS, application control, URL filtering, and VPN support (site-to-site and remote access SSL/IPsec).
4. Data Center Cabling & Accessories
Horizontal and vertical structured cabling within racks.
Patch panels, cable management, and labeled termination.
Grounding, bonding, and surge protection.
5. Structured Cabling (Data & Voice)
Supply and install one data outlet (Cat 6A) per employee workstation – total of 130 outlets + spares (approx. 10%).
Each outlet serves both data and Cisco IP phone (dual port faceplate or daisy chained through phone switch).
Cabling from workstations to floor distribution racks (telecommunications rooms) on each floor.
OM4 multimode fiber or OS2 single mode fiber between main distribution (data center) and floor distribution racks.
Redundant backbone links.
6. Cisco IP Telephony System
Supply and install Cisco Unified Communications Manager (Call Manager) or Cisco Business Edition appliance.
Cisco IP phones for all 130 employees (model: e.g., Cisco 7841 or 8851 with PoE).
Voice VLAN configuration with QoS (DSCP/CoS) across all switches.
Extension to extension calling, call forwarding, hunt groups, auto attendant.
Voicemail (Cisco Unity Connection).
Integration with existing PSTN lines or SIP trunk.
7. Cisco Wi-Fi Solution
Supply and install Cisco Wi-Fi access points (Catalyst 9164 series).
Number determined by site survey (minimum coverage for 2,800 m² over 3 floors, with overlapping cells for seamless roaming).
Ceiling or wall mount as required.
Cisco wireless controller (physical appliance or virtual) with licenses for all APs.
Guest Wi-Fi with captive portal and bandwidth limits.
WPA3 Enterprise with 802.1X authentication using RADIUS (integration with Active Directory).
8. Access Control System (Honeywell)
Supply and install: electric locking device (magnetic lock or electric strike).
Supply and install: door contact sensor (open/close status).
Supply and install: request to exit (REX) motion sensor or push button.
Supply and install: proximity card reader (13.56 MHz, support for MIFARE or similar).
Supply and install: emergency break glass or manual override where required (fire code compliance).
Networked access control panels (one per floor).
Access control server software (on premises) with database of up to 500 users (expandable).
Configuration of schedules, access levels, and audit trails.
9. Time Attendance System
Supply and install biometric (fingerprint) or RFID time attendance terminals at main entrances (quantity: 4 units – main entrance, back door, and two floor entries).
Terminals to be networked (PoE or Wi-Fi) and integrated with access control system.
Integration with Active Directory for user management.
Time attendance software on-premises for: employee clock-in/out logging, shift scheduling, overtime calculation, and absence tracking, and export to payroll system (e.g., CSV/Excel).
10. Conference Room System
Supply and install all-in-one conference room solution or separate components: large format display (86-inch, 4K, Sony), PTZ camera (4K, wide angle, auto-framing), ceiling microphone array, full-range sound bar or speakers + amplifier, wireless presentation system (Crestron AirMedia), and meeting room controller (touch panel) for one-touch join.
Support for Microsoft Teams, Zoom, or Webex (licensed as required).
HDMI and USB plug-and-play connectivity for laptops.
Basic wall panels or acoustic ceiling tiles if required for echo reduction.
11. Additional Scope Elements
Supply and install Cisco Catalyst switches (PoE+) to power: IP phones (130 units), Wi-Fi access points (26 units), access control doors (12 units), time attendance terminals (4 units), and conference room devices (12 units).
Stackable switches per floor, with 10Gb uplinks to data center.
Data center UPS: online double-conversion UPS (e.g., 10–20 kVA) with runtime for servers, storage, routers, firewall, core switches.
Floor distribution racks: small UPS (1–2 kVA) for intermediate switches and small PoE devices.
Data center: 2x 42U server racks (front/rear perforated doors, cable management).
Floor telecom rooms: 1x 15U or 22U wall-mount or floor-mount swing rack per floor.
Single sign-on (SSO) where possible (Active Directory integration for Wi-Fi, access control, time attendance, file server).
Central logging and monitoring, syslog server.