Scope of work (Low Current System)
Supply, installation, testing, and commissioning of a complete Carbon Film Electric Radiant Floor Heating System. The project covers a total heated area of 12,700 square meters. The selected system must be capable of functioning as the primary heat source for these zones, providing a comfortable, energy-efficient, and low-maintenance solution suitable for a high-traffic commercial hospitality environment.
1. Electrical Infrastructure & Control
Dedicated Circuits: Provide and install dedicated electrical circuits from the main distribution panel to serve the heating load of each room/zone.
Thermostats: Supply and install programmable thermostats for each thermal zone (per room or per logical heating area), with each room capable of controlling its own temperature independently.
Protection: Protect each heating circuit with a dedicated 30mA Residual Current Device (RCD) to ensure electrical safety.
Installation Boxes: Provide and install junction boxes for all electrical terminations – a 25mm deep junction box at the thermostat location, and a separate 4-inch x 4-inch electrical box for connections.
Cabling: Run all connection cables from the thermostat to the heating film embedded in cut channels within the insulation layer, or within conduit, to avoid creating pressure points under the finished floor.
2. Subfloor Preparation & Heating System Installation
Insulation Layer: Supply and install a high-quality extruded polystyrene (XPS) or polyurethane foam insulation board (6mm Depron, or thicker 12mm where applicable) across the entire prepared subfloor.
Channels for Cabling: Mechanically cut channels (grooves) into the insulation layer to accommodate the floor sensor probe and the connection wires.
Heating Film Layout: Unroll and cut the carbon heating film according to a detailed layout plan, cut at designated intervals to fit the dimensions of the room, with the floor covering (laminate / luxury vinyl tile) compatible and rated for use with underfloor heating.
Protective Layer: After laying and connecting the film, install a protective polyethylene overlay board or similar protection layer to shield the heating elements before the final floor finish is installed.
Sensor Placement: Install the floor temperature sensor in one of the pre-cut channels in the insulation layer, positioned centrally within the heated area.
3. Finishing, Commissioning & Documentation
Final Floor Covering: Lay the specified hotel-grade floor finish (LVT, or engineered wood) over the protective layer.
Electrical Testing: Conduct mandatory electrical testing of the system before and after the final floor covering is installed – an Insulation Resistance Test (Megger) to ensure the heating elements are not damaged and there is no short to ground, and a Continuity Test to verify the integrity of all electrical connections.
Commissioning: Energize the system to commission its operation, and verify that all thermostats communicate correctly with their respective heating zones and sensors.
Handover Documentation: Upon completion, provide complete as-built documentation to the client.